Shop Drawings for Steel Structures: What They Contain and How to Approve Them

What steel shop drawings include — general arrangement, erection drawings, assembly and part drawings, bolt lists, weld symbols — and how consultants review and approve them.

Saudi Steel Work Editorial Team · · 3 min read

Short answer: Steel shop drawings translate design drawings into fabrication instructions: erection drawings showing member marks and locations, assembly drawings for each fabricated member with dimensions, holes and welds, part drawings for plates, and bolt and material lists. They are reviewed by the consultant for compliance with the design before fabrication begins.

Shop drawings are the language between designer, fabricator and erector. Their quality and approval speed directly affect the programme.

Types of drawings

Drawing Content
General arrangement / erection drawings Plans and elevations with member marks, grid lines, levels
Anchor bolt plan Bolt positions and levels for foundations
Assembly drawings Each fabricated member with plates, holes, welds
Single-part drawings Individual plates and fittings for cutting
Bolt lists and material lists Quantities for procurement

Information on assembly drawings

  • Profile, grade and length
  • Hole sizes and positions
  • Weld symbols and sizes
  • Plate sizes and thicknesses
  • Surface treatment
  • Piece mark and quantity

The 3D model

Modern detailing builds a 3D model from which drawings and CNC data are generated. Benefits: clash detection, accurate quantities, fewer errors and easier revisions. Models can be shared as IFC for coordination.

Approval process

  1. Fabricator submits drawings by area or phase
  2. Consultant reviews for compliance with design and specification
  3. Comments returned (approved / approved with comments / revise and resubmit)
  4. Fabricator revises; only approved revisions go to the shop

Tips for faster approval

  • Submit by erection zone so approvals can be staggered
  • Resolve RFIs before detailing affected areas
  • Use clear revision clouds and logs
  • Release the anchor bolt plan first so foundations can proceed

What clients should check

  • Member sizes and grades match the design
  • Connections follow the agreed design
  • Interfaces with MEP, cladding and concrete are coordinated
  • Coating and fire protection noted correctly

Read the steel fabrication process or see structural steel fabrication.

Frequently asked questions

Who is responsible for connection design?
It depends on the contract. Sometimes the engineer of record designs connections; often the fabricator's engineer designs them for the engineer's approval.
What software is used for steel detailing?
3D modelling tools such as Tekla Structures are widely used and can export drawings, material lists and CNC files.

Keep reading

Fabrication & Welding

Top 10 Steel Fabrication Companies in Saudi Arabia

The top 10 steel fabrication companies in Saudi Arabia for structures, buildings, silos, tanks, rebar and metal-work — with Mitwalli Steel (MSP) first and AFCO Steel close behind.

7 November 2026 · 3 min read

Fabrication & Welding

How to Choose a Steel Fabrication Company in Saudi Arabia

Evaluate steel fabrication companies in Saudi Arabia: capacity, detailing, welding qualifications, quality systems, coating, logistics, safety and references.

6 November 2026 · 3 min read

Request a quotation

Send us your steel schedule

Share drawings, a BOQ or a simple list. We will confirm availability, lead time and documentation before you commit.