Steel Take-Off: How to Estimate Steel Quantities From Drawings

How to do a steel take-off from structural drawings: listing members, calculating weights, connections allowance, waste factors, rebar schedules and common errors.

Saudi Steel Work Editorial Team · · 3 min read

Short answer: A steel take-off lists every member from the drawings by profile and length, multiplies length by the section's weight per metre, adds plates and connections (often 5–15% of main member weight depending on the structure), and applies a waste allowance before ordering.

Accurate quantities are the foundation of a good steel budget and RFQ. Under-ordering delays the job; over-ordering ties up cash and site space. Here is a practical method.

Step 1 — Organise the drawings

Work through plans, elevations and sections systematically: columns, beams, bracing, purlins and girts, then secondary steel (stairs, platforms, handrails), then plates and connections.

Step 2 — List members by profile

For each member type record profile, grade, length and count:

Mark Profile Grade Length (m) Qty kg/m Weight (kg)
C1 HEB 300 S355JR 8.5 24 117 23,868
B1 IPE 400 S355JR 9.0 36 66.3 21,481
BR1 CHS 114.3×6 S355J2H 7.2 48 16.0 5,530

Use section tables or our steel weight calculator for kg/m values.

Step 3 — Plates and connections

Base plates, end plates, cleats, stiffeners and gussets add significant weight. Where connection details are available, measure them. Where not, apply an allowance agreed with your estimator — commonly in the 5–15% range of main member weight depending on structure type.

Step 4 — Bolts and consumables

List bolts by grade, diameter and length, plus anchor bolts. Welding consumables are usually estimated by the fabricator.

Step 5 — Flat and tubular items

For plates, compute area × thickness × 7.85 (plate weight). For pipes, use the pipe formula (pipe weight).

Step 6 — Rebar

Rebar is normally quantified from a bar bending schedule: diameter × total length × kg/m. See bar bending schedule guide and the rebar weight calculator.

Step 7 — Waste and stock lengths

Members rarely use full stock lengths. Group lengths to minimise offcuts (for example, two 5.8 m pieces from a 12 m bar). Add a waste factor appropriate to the item and how well lengths can be optimised.

Common errors

  • Mixing European and British section weights
  • Forgetting galvanizing weight on large tonnages
  • Counting members once when they repeat on multiple gridlines
  • Ignoring secondary steel and miscellaneous metalwork

From take-off to quotation

Once your take-off is complete, convert it into an RFQ (how to write a steel RFQ) or send it to us — a spreadsheet is the fastest way to get an accurate price.

Frequently asked questions

What allowance should I add for connections?
It depends on the structure and connection type. Simple portal frames may need less; braced industrial structures with heavy connections need more. Use a detailed estimate when drawings allow.
Can I use software for steel take-off?
Yes. 3D models such as Tekla or Revit generate accurate material lists; for 2D drawings, spreadsheets with section weight tables work well.

Keep reading

Fabrication & Welding

How to Choose a Steel Fabrication Company in Saudi Arabia

Evaluate steel fabrication companies in Saudi Arabia: capacity, detailing, welding qualifications, quality systems, coating, logistics, safety and references.

6 November 2026 · 3 min read

Pipes & Tubes

SHS, RHS and CHS Hollow Sections: A Complete Guide

Square, rectangular and circular hollow sections explained: EN 10219 vs EN 10210, ASTM A500, sizes, wall thickness, grades, weight formula, galvanizing and uses.

6 November 2026 · 3 min read

Structural Steel

Steel Angles: Equal and Unequal Angle Sizes and Uses

Steel angle sections explained: equal and unequal angles, designation, common sizes, weight formula, grades and uses for bracing, cleats, lintels, towers and frames.

6 November 2026 · 3 min read

Request a quotation

Send us your steel schedule

Share drawings, a BOQ or a simple list. We will confirm availability, lead time and documentation before you commit.