How to Compare Steel Quotations Line by Line

Steel quotations often look similar but are not comparable. Learn how to normalise grade, size, weight basis, certificates, delivery and VAT to compare offers fairly.

Saudi Steel Work Editorial Team · · 3 min read

Short answer: To compare steel quotations fairly, put every offer on the same basis: identical grade and standard, the same weight basis (theoretical or actual), the same certificates, the same delivery terms, and prices before VAT per tonne and per item. Only then compare price and lead time.

Three quotations for the "same" steel list can differ by 10% or more — and the cheapest is often not the best value. The difference is usually hidden in the basis of the price rather than the price itself. Here is how to compare offers properly.

Build a comparison sheet

Create one row per item and one column group per supplier. For each item record:

  • Grade and standard offered
  • Size, length and quantity offered
  • Unit (per tonne, per piece, per metre)
  • Weight basis — theoretical or actual
  • Unit price excluding VAT
  • Lead time and stock status
  • Certificates included

Any cell that differs from your enquiry should be highlighted. Those differences are where risk sits.

Normalise the weight basis

Steel is commonly priced per tonne, but suppliers may invoice on theoretical weight (from section tables) or actual weighed weight. Mills roll within tolerances, so actual weight can be a few percent above or below theoretical. A slightly lower price per tonne on actual weight can end up more expensive than a theoretical-weight offer. Our steel weight calculator helps you estimate theoretical weights for checking.

Check grade substitutions

Look carefully for:

  • S275 offered where S355 was requested
  • ASTM A53 offered instead of A106 for high-temperature pipe
  • Cold-formed hollow sections offered instead of hot-finished
  • Pre-galvanized tube offered instead of hot-dip galvanized after fabrication

Any of these may be acceptable — but only with the engineer's approval, and they are not like-for-like on price.

Compare certificates and testing

An offer with EN 10204 3.1 certificates, impact testing or ultrasonic testing costs more than one with a basic 2.2 test report. If your specification needs these, cheaper offers that exclude them are incomplete, not cheaper. See mill test certificates explained.

Align delivery terms

Term on quotation What you still pay for
Delivered to site, offloaded Usually nothing extra
Delivered to site, not offloaded Crane or forklift at site
Ex-works / ex-warehouse Transport, loading, offloading
FOB / CFR (imports) Freight, insurance, customs clearance, port charges, inland transport

For imports, see Incoterms for steel purchases.

Watch price validity and escalation

Steel prices move. A quotation valid for three days is not comparable to one valid for thirty. Escalation clauses linked to mill price changes shift risk back to you. Read our guide to price validity and payment terms.

Compare lead time with your programme

A cheaper offer that arrives two weeks late can cost more in idle labour and cranes than the price difference. Map each supplier's lead time against your required-on-site date.

Final check

Before awarding, confirm in writing: grade, standard, quantity, weight basis, certificates, delivery terms, price validity, payment terms and VAT. Then issue a purchase order that repeats those terms exactly.

Need a quotation that is easy to compare? Send your steel list and each line will show grade, basis, lead time and documents.

Frequently asked questions

What is theoretical weight versus actual weight?
Theoretical weight is calculated from nominal dimensions and density; actual weight is measured on a weighbridge. Rolling tolerances mean the two differ, so quotations must state which basis applies.
Should transport be included when comparing steel prices?
Yes. Compare delivered-to-site prices, or add a realistic transport and offloading cost to ex-works offers.

Keep reading

Buying Guides & Procurement

How to Write a Steel RFQ That Gets Accurate Prices

Write a steel request for quotation (RFQ) that suppliers can price accurately: item list, grades, standards, tolerances, certificates, delivery, commercial terms and a template.